Subcontractors Spar Over Tenn. DOE Complex Costs

Law360, New York (April 15, 2011, 6:51 PM EDT) -- A third-party defendant in a fight over compensation for a $119 million government complex contract in Tennessee filed a lawsuit against a subcontractor Thursday accusing it of causing costly delays on the project.

In a fourth-party complaint filed in the U.S. District Court for the Eastern District of Tennessee, Babcock & Wilcox Technical Services Y-12 LLC alleged that Parsons Infrastructure & Technology Group Inc. submitted faulty design materials for the construction of an uranium plant in Oak Ridge, Tenn., causing $64 million in delays on the...
To view the full article, register now.