Tribe Involvement Thwarts Enable Midstream's Easement Bid
An Oklahoma federal judge on Thursday nixed efforts by Enable Midstream Partners LP to condemn an easement over tribal land for the company's natural gas pipeline, saying the Kiowa Tribe's ownership interest in the land prevented her from granting the easement.
-
April 06, 2016
Energy Co. Pushes To Combine Tribal Pipeline Suits
Enable Midstream Partners LP continued to press an Oklahoma federal court Tuesday to combine its condemnation bid with a suit by tribal landowners over the company's continued use of a gas pipeline on land held in trust by the federal government, saying that the disputes are "closely intertwined."
-
March 29, 2016
Tribal Landowners Urge Judge To Keep Pipeline Claims Apart
Tribal landowners urged an Oklahoma federal judge Monday not to combine their suit against Enable Midstream Partners LP over the company's continued use of a gas pipeline on land held in trust by the federal government with the company's condemnation bid, saying the cases present no common issues of law or fact.
-
November 12, 2015
Pipeline Co. Wants Perpetual Right-Of-Way On Trust Land
An Oklahoma pipeline company asked a federal court on Wednesday to green-light eminent domain proceedings on a small parcel of Native American trust land for a perpetual right-of-way to operate its underground natural gas pipeline, saying in a complaint that it's been unable to obtain the necessary consent.