February 22, 2024
A subcontractor and its professional liability insurer have reached a settlement in principle on about $5 million in underlying claims over moldy, defective wooden framework the subcontractor supplied to a senior living project, the parties told a Florida federal court.
November 01, 2023
A subcontractor told a Florida federal court that its professional liability insurer owes it $2.4 million in defense costs and $2.5 million for a final award in an arbitration over alleged design flaws and mold issues in an Atlantic Beach senior living project.