Divided Ohio High Court Greenlights Wind Farm

Law360, New York (March 6, 2012, 6:40 PM EST) -- The Supreme Court of Ohio ruled Tuesday that "there is no need for delay" of an EverPower Wind Holdings Inc. affiliate's plans to build a 126-megawatt wind farm despite landowners and local officials' concerns over noise, safety and the fate of old turbines.

The state agency in charge of approving major utility projects, the Power Siting Board, was right to give the green light to EverPower affiliate Buckeye Wind LLC to build one of the state's first wind farms west of Columbus, the high court ruled...