Split Fed. Circ. Tosses Iraq Contract Claim As Premature

Law360, New York (April 23, 2012, 7:17 PM EDT) -- A divided Federal Circuit on Friday dismissed a contractor's auditor-backed attempt to collect $2.5 million still owed to a subcontractor on Iraq building projects, saying the contractor couldn't sue for the unpaid claim under the Contract Disputes Act unless the government disputes it.

Parsons Global Services Inc. sought $2.5 million to pay subcontractor Odell International Inc., which underbilled for its services in Iraq, as determined the Defense Contract Audit Agency. While Odell and Parsons were denied when they asked their contracting officer for the money, the...