NYSPSC Rebuffs Enviro Report On $2B Blackstone Power Line

Law360, New York (August 31, 2012, 5:36 PM EDT) -- A New York regulator on Thursday denied requests from two state agencies and Entergy Corp. to consider a Consolidated Edison Co. report on the potential environmental impact of the Blackstone Group LP’s planned $2 billion power line from Quebec to New York City.

Administrative Law Judge Michelle L. Phillips rejected the New York Department of Environmental Conservation and Department of Public Service trial staff's effort to have the New York State Public Service Commission take official notice of a Resource and Recovery Act draft report prepared...