Bombardier Says Sub Caused Delays In Airport Train Project

Law360, Wilmington (October 21, 2013, 9:04 PM ET) -- Bombardier Transportation (Holdings) USA Inc. on Monday sued a subcontractor in Pennsylvania federal court, saying the company’s shoddy engineering work on a train system at the joint civil-military Phoenix Sky Harbor International Airport caused a two-month delay and cost millions to repair.

In the suit in the Western District of Pennsylvania, Pittsburgh-based Bombardier accuses Phoenix-based engineering firm The CK Group Inc. of breach of contract for allegedly refusing to pay the cost of demolishing, redesigning and reconstructing a substantial portion of the track for the PHX...
To view the full article, take a free trial now.
Try Law360 for free for seven days
Already a subscriber? Click here to login

Already have access?

  1. Forgot your password?
  2. Sign In

Get instant access to the one-stop news source for business lawyers

Required

Case Information

Case Title

BOMBARDIER TRANSPORTATION (HOLDINGS) USA, INC. v. THE CK GROUP, INC.

Case Number

2:13-cv-01526

Court

Pennsylvania Western

Nature of Suit

Contract: Other

Judge

Mark R. Hornak

Date Filed

October 21, 2013

Sections

Law Firms Mentioned

Companies Mentioned