NJ Architecture Firm Dodges $3M Cost Overrun Suit

Law360, New York (October 25, 2013, 2:07 PM EDT) -- After previously failing to have claims against it dismissed, a New Jersey architecture firm on Thursday was finally tossed from a contractor's $3 million cost overrun suit filed against the Atlantic City Housing Authority over the construction of a housing project.

Senior District Judge Joseph E. Irenas finally granted Lindemon Winckelmann Deupree Martin Russell & Associates PC's motion for summary judgment, finding that SRC Construction Corp., which filed the complaint, had failed to present material evidence to prove Lindemon's negligence. 

In the same ruling, Irenas refused...