Hunt Construction Group, Inc. et al v. Alberici Constructors, Inc.
Case Number:
1:16-cv-24405
Court:
Nature of Suit:
Judge:
Firms
Companies
Sectors & Industries:
-
December 12, 2016
Dolphins Stadium Suit Is In Proper Court, Subcontractor Says
A subcontractor tangling with a construction management firm and the owner of the Miami Dolphins stadium over cost overruns incurred in installing a new steel canopy at the sports venue said Monday that although the prime contractor may choose to arbitrate or litigate the dispute, it cannot dictate court jurisdiction.
-
November 03, 2016
Dolphins Stadium Owner Wants Canopy Case Moved
A construction management firm and the owner of the Miami Dolphins stadium asked a Florida federal judge on Wednesday to remand to state court their countersuit against a subcontractor in a dispute over cost overruns incurred in installing a new steel canopy at the sports venue.
-
October 24, 2016
Subcontractor Fights Countersuit In $78M Dolphins Spat
A subcontractor that sued the Miami Dolphins and an AECOM unit over cost overruns for a new steel canopy on the NFL team's stadium asked a Florida federal court Friday to dismiss the team's countersuit against it, calling it an attempt to get an advance ruling on a potential affirmative defense.
-
October 19, 2016
Miami Dolphins, Contractors Spar Over $78M Stadium Canopy