By Linda Chiem ( July 28, 2014, 8:24 PM EDT) -- The state of Alaska on Friday urged the Federal Energy Regulatory Commission to reject an attempt by operators of the Trans-Alaska Pipeline System to recover "ineligible" costs from ratepayers for an ill-planned, still-unfinished $786 million reconfiguration project to electrify the pipeline's turbines....