GEORGE HARMS CONSTRUCTION CO., INC. et al v. GATEWAY DEVELOPMENT COMMISSION et al

  1. December 11, 2025

    NJ Judge Won't Lift Bid Deadline On Tunnel Rail Project

    A New Jersey federal judge said Thursday she won't lift a deadline to bid on a railway-construction project associated with building a new tunnel to New York City, saying a New Jersey construction company isn't likely to win its challenge to a project labor agreement tied to the venture.

  2. December 09, 2025

    NJ Builder Says Court Can Decide Tunnel Labor Row

    The Third Circuit's finding that federal labor law blocks courts from stopping National Labor Relations Board cases doesn't apply to a builder's bid to block an imminent bidding deadline on the lucrative Hudson Tunnel Project, the builder and a unionized employee told a New York federal judge.

  3. November 19, 2025

    NJ Construction Co. Sues Over Hudson Tunnel Union Limits

    A New Jersey construction company wants to delay bidding for part of the $16 billion Hudson Tunnel Project, claiming in a federal lawsuit that the multistate commission overseeing the project unlawfully barred employing the United Steelworkers union currently representing the company's workers.