April 19, 2012
Shaw Group Inc.'s claims that it is owed $1.1 billion by two GenOn Energy Inc. units for a contract to install pollution control equipment on three power plants remained alive Wednesday when a New York federal judge mostly denied competing summary judgment bids.
December 23, 2011
Stone & Webster Inc. and two GenOn Energy Inc. units traded blows Thursday over whether GenOn owes the engineering contractor $1.1 billion in unpaid funds for a contract to install pollution control equipment on three power plants.