November 18, 2011
A Washington federal judge on Friday refused to block the U.S. Department of Energy from funding the construction of a $2.4 billion power plant in Mississippi, nixing the Sierra Club's preliminary injunction request and its claims challenging potential loan guarantees.
May 17, 2011
The Sierra Club asked a Washington court Monday to prohibit the U.S. Department of Energy from funding the construction of a $2.4 billion power plant in Mississippi until the department remedies alleged violations of the National Environmental Policy Act.