$2.6B Ky. Bridge Project Survives Enviro Challenge
A Kentucky federal judge on Wednesday dismissed a suit brought by the Coalition for the Advancement of Regional Transportation challenging a $2.6 billion bridge project to Indiana, finding that state and federal transportation authorities had exercised reasonable discretion in the project's planning.
-
February 26, 2013
US Wants Claims Pared From $2.6B Ky. Bridge Challenge
The Federal Highway Administration has asked a Kentucky judge to toss a coalition's claims under two federal acts challenging a $2.6 billion bridge project to Indiana, arguing the project's environmental review and tolling plans are in line with the laws, according to a Monday filing.
-
January 07, 2013
Settlement Paves Way For $2.6B Ohio River Bridge Project
The state transportation departments of Kentucky and Indiana agreed Friday to pay $1.7 million to settle a long-running suit brought by an environmental group and a historic preservation group that sought to block a $2.6 billion project to construct new bridges across the Ohio River.
-
November 08, 2012
Judge Won't Halt Early Work On $2.6B Ky. Bridge Project
A Kentucky federal judge on Thursday rejected a transportation and environmental nonprofit's effort to stall preliminary work on a $2.6 billion bridge project connecting the state to Indiana, finding the injunction bid to be premature at such an early stage in the case.
-
September 20, 2012
Group Seeks Injunction On $2.9B Louisville Bridge Project
A transportation and environmental activist nonprofit asked a Kentucky federal judge on Wednesday for an injunction to block the construction of a $2.9 billion bridge project connecting the state to Indiana, arguing the work would cause harm and violate its due process rights.
-
August 10, 2012
$4.5B Louisville Bridges Can Advance While Case Builds
A Kentucky federal judge on Wednesday allowed construction to proceed on a $4.5 billion, long-delayed plan to build two bridges over the Ohio River connecting southeast Indiana to Louisville, Ky., but gave groups challenging the project until February to submit final claims.