February 28, 2013
Two challenges to a Southern California wind project were struck down Wednesday when a federal judge nixed a Native American tribe's claims that the site's history hadn't been properly researched and tossed an environmental group's allegations that an impact statement was flawed.
October 01, 2012
A California federal judge on Friday denied a motion by a coalition of environmental groups and a local union to halt construction of a wind energy facility, ruling that the potential harm to local bird species was not likely to be substantial.
May 29, 2012
A California environmental group, a local labor union and desert residents on Friday sued federal and state authorities to stop the construction of a 315-megawatt wind energy facility on more than 10,000 acres of public land near the Anza-Borrego Desert State Park.