United States of America v. CCM TCEP, LLC et al

Track this case

Case overview

Case Number:

1:21-cv-01461

Court:

Delaware

Nature of Suit:

Contract: Other

Judge:

Todd M. Hughes

Firms

Companies

Sectors & Industries:

  1. July 14, 2022

    Judge Axes Coal Plant Guarantors' $86M Claims Against Feds

    A Delaware federal court ruled companies that guaranteed a failed coal power plant project can't seek $86 million from the federal government for its collapse because they aren't party to the original contract for the facility's construction.

  2. March 02, 2022

    Power Plant Backers Say Feds Not Immune From $86M Claim

    Two companies that guaranteed a stalled coal power plant project in Texas fought the federal government's bid to ditch claims it owes $86 million for allegedly dooming the project, arguing the government can't claim immunity from a fight it started. 

  3. October 18, 2021

    Feds Seek $13.8M In Clean Coal Project Contract Breach Suit

    The U.S. Department of Energy wants $13.8 million from two companies that guaranteed the now-stalled construction of a Texas coal power plant with carbon capture and sequester capabilities, saying the companies violated contracts that kept funding for the project coming.

Hello! I'm Law360's automated support bot.

How can I help you today?

For example, you can type:
  • I forgot my password
  • I took a free trial but didn't get a verification email
  • How do I sign up for a newsletter?
Ask a question!