  1. December 22, 2016

    Duke Energy Owes $34M On Scrapped Fla. Plant, Judge Says

    A North Carolina federal judge ruled Thursday that Westinghouse Electric Company can't recoup $500 million in development costs over a now-scrapped $24.7 billion nuclear power plant in Florida, but is entitled to a $30 million termination fee plus $4 million in interest from Duke Energy Florida Inc.

3 other articles on this case. View all »

Parties

Stay ahead of the curve

In the legal profession, information is the key to success. You have to know what’s happening with clients, competitors, practice areas, and industries. Law360 provides the intelligence you need to remain an expert and beat the competition.


  • Direct access to case information and documents.
  • All significant new filings across U.S. federal district courts, updated hourly on business days.
  • Full-text searches on all patent complaints in federal courts.
  • No-fee downloads of the complaints and so much more!

TRY LAW360 FREE FOR SEVEN DAYS

Hello! I'm Law360's automated support bot.

How can I help you today?

For example, you can type:
  • I forgot my password
  • I took a free trial but didn't get a verification email
  • How do I sign up for a newsletter?
Ask a question!