P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. et al

  1. May 26, 2023

    Judge Dismisses All Claims In $24M Mich. Asbestos Row

    A Michigan federal judge has ended a messy dispute between demolition and remediation companies, a power plant owner and an insurer over almost $24 million in allegedly unpaid costs for removing asbestos and other hazardous materials from a decommissioned power plant.

  2. May 28, 2020

    Power Plant Co. Can't Nix All Claims In $24M Asbestos Row

    An asbestos abatement company can pursue some of its claims that a power plant owner is unfairly benefiting from its refusal to pay the extra costs for a project that ballooned from $8 million to nearly $24 million, a Michigan federal court said Thursday.

  3. June 04, 2019

    Asbestos Removal Biz Seeks $24M For Extra Demolition Work

    An asbestos removal company has alleged in Michigan federal court that it is owed at least $23.8 million for work performed on a demolition project, saying it was misled on the amount of work needed to remove contaminated material, which required various contract changes.