February 07, 2020

United States of America v. Guam Power Authority et al

Track this case

Case Number:

1:20-cv-00007

Court:

Guam

Nature of Suit:

Environmental Matters

Judge:

Frances M. Tydingco-Gatew

View recent docket activity


Reflects complaints, answers, motions, orders and trial notes entered from Jan. 1, 2011.
Additional or older documents may be available in Pacer.


Coverage

  1. February 07, 2020

    Guam Utility Will Replace Plant, Pay $400K To End EPA Action

    Guam's municipal utility has committed to the planned retirement and replacement of an existing power plant, upgrades to another plant and a $400,000 civil penalty as part of a settlement unveiled Friday with the U.S. Environmental Protection Agency that resolves allegations of emissions standards violations.


Parties

Stay ahead of the curve

In the legal profession, information is the key to success. You have to know what’s happening with clients, competitors, practice areas, and industries. Law360 provides the intelligence you need to remain an expert and beat the competition.


  • Direct access to case information and documents.
  • All significant new filings across U.S. federal district courts, updated hourly on business days.
  • Full-text searches on all patent complaints in federal courts.
  • No-fee downloads of the complaints and so much more!

TRY LAW360 FREE FOR SEVEN DAYS