December 14, 2023
Claims that a renewable energy developer intentionally delayed the construction of a 126-megawatt wind project to avoid paying out nearly $70 million from soon-to-expire federal tax credits are not supported by evidence, a New York federal judge ruled Thursday, following the completion of a bench trial.