National Wildlife Refuge Association et al v. United States Army Corps of Engineers et al

  1. March 02, 2022

    Wis. Judge Blocks $500M Power Line From Wildlife Refuge

    A $500 million Midwest transmission line faces an uncertain future after a Wisconsin federal judge said building it would violate wildlife refuge protections, an order that essentially barred developers from the path they've been banking on.

  2. October 20, 2021

    Court Told To Nix 'Afterthought' Bid To Halt $500M Power Line

    The developers behind a 102-mile, $500 million high-voltage transmission line project in the Midwest urged a Wisconsin federal court to reject conservationists' attempt to put a hold on construction, arguing the groups can't claim it's an emergency when their own delay created the time crunch.

  3. September 07, 2021

    Feds Say Approvals Of $500M Power Line Were Sound

    The federal government is seeking to shut down conservationists' fight against a 102-mile, $500 million high-voltage transmission line project in the Midwest, arguing a very small portion of the proposal required federal approvals and the authorizations issued were by the book.

  4. May 05, 2021

    Coalition Launches 2nd Fight Against Power Line Project

    Four conservation groups have launched another line of assault against a 102-mile, $500 million high-voltage transmission line project in the Midwest on Wednesday, this time alleging that the U.S. Army Corps of Engineers didn't adequately study how local water quality will be effected.