January 27, 2026
A Massachusetts federal judge on Tuesday lifted a Trump administration freeze on the nearly complete Vineyard Wind offshore energy project, saying the government had likely flouted federal law by failing to explain a "disconnect" between its stated concerns about national security and its willingness to allow completed turbines to continue operating.
January 16, 2026
Vineyard Wind has filed a suit in Massachusetts federal court urging a judge to let it finish work on a $4.5 billion, 800 megawatt offshore wind energy project that was due to be completed by the end of March before being halted by the Trump administration.