Fluor Enterprises, Inc. v. Duke Energy Florida, LLC

Track this case

Case Number:

8:19-cv-00224

Court:

Florida Middle

Nature of Suit:

Contract: Recovery/Enforcement

Judge:

William F. Jung

Firms

Companies

Sectors & Industries:

View recent docket activity


Reflects complaints, answers, motions, orders and trial notes entered from Jan. 1, 2011.
Additional or older documents may be available in Pacer.


Coverage

  1. January 29, 2019

    Fluor Sues Duke Energy Over Tapping Of $67M Credit Letter

    Fluor Enterprises alleged in Florida federal court on Tuesday that Duke Energy swiped a $67 million letter of credit that was issued in the event a generator facility wasn’t completed, claiming the company never provided a cost breakdown of delays associated with the project.