June 09, 2026
A Colorado district judge has partially blocked the federal government's approval of a 226-mile, 345-kilovolt electricity transmission line in the Nebraska Sandhills, finding that the U.S. Fish and Wildlife Service bypassed required cultural resource and environmental consultations without proving that an emergency existed under a presidential executive order.