Gov't Doesn't Have To Reimburse KBR For Delays, Army Says

By Kaitlyn Burton (October 29, 2019, 8:34 PM EDT) -- The Army urged the Federal Circuit to back a contracting board's decision sparing it from having to pay Kellogg Brown & Root Services Inc. more than $48 million for military escort delays, saying that KBR's deal with a subcontractor barred compensation for such delays.

In response to KBR's appeal of the Armed Services Board of Contract Appeals' decision, the Army said it shouldn't be held liable for additional expenses KBR paid a subcontractor to install live-in trailers for troops at U.S. military bases in Iraq.

The Army's Logistics Civil Augmentation Program contract, or LOGCAP III, was inked to provide support services...

Stay ahead of the curve

In the legal profession, information is the key to success. You have to know what’s happening with clients, competitors, practice areas, and industries. Law360 provides the intelligence you need to remain an expert and beat the competition.


  • Access to case data within articles (numbers, filings, courts, nature of suit, and more.)
  • Access to attached documents such as briefs, petitions, complaints, decisions, motions, etc.
  • Create custom alerts for specific article and case topics and so much more!

TRY LAW360 FREE FOR SEVEN DAYS

Hello! I'm Law360's automated support bot.

How can I help you today?

For example, you can type:
  • I forgot my password
  • I took a free trial but didn't get a verification email
  • How do I sign up for a newsletter?
Ask a question!